Dispatch Supervisor

Transgas is hiring a Dispatch Supervisor for our Dispatch Operations department in Lowell, MA.

Job Purpose

The position of Dispatch Supervisor reports directly to the Director, Dispatch Operations. This position is responsible for developing schedules, booking drivers with the appropriate equipment, handling customer service requests, analyzing driver’s daily trips, and supervising union drivers. This is a shift position requiring rotating weekend and holiday coverage.

Key Accountabilities

Position Responsibilities (including but not limited to):

  • Customer satisfaction
  • Schedule loads
  • Assign drivers work on a daily basis
  • Assign units for cost-effective utilization
  • Ensure accurate record-keeping
  • Regulatory complianc.
  • Supervise, train and hold drivers accountable for their daily actions. Supervise a culturally diverse workforce through coaching, counseling and team building to ensure tasks are carried out in an efficient manner.
  • Oversee the operational workload of team; ensuring allocated staff are fully utilized in order to deliver against agreed program of work
  • Train, test, and develop LNG drivers (and document training) to ensure staff have the required skills and knowledge to successfully operate CDL and LNG vehicles and ensure compliance with regulations; ensure supervised team comply with safety standards, policies and processes in order to ensure a safe working environment and minimize risk for all staff
  • Communicate maintenance, operating and training information as well as changes to procedures others as necessary in order to ensure that records are contemporary and accurate
  • Maintain compliance with relevant regulations by providing up to date information on Transgas and National Grid policies, processes and programs to regulatory bodies
  • Develop, edit, verify, promote and implement procedural best practices (e.g. operations, isolation, maintenance) within the team in order to ensure all working practices are compliant with Transgas and National Grid policies and regulatory requirements
  • Monitor and challenge business processes where appropriate in order to ensure Transgas is compliant with regulatory requirements
Qualifications
  • Associates degree preferred and 3+ years experience in a supervisor management position
  • Trucking industry and/or LNG industry experience is a plus
  • Valid drivers license
  • CDL (Commercial Driver’s License) / Tanker / HazMat endorsements is a plus
  • Proficiency in computer skills including Microsoft Office
  • Demonstrated strong verbal and written communication skills
  • Must have experience managing a team with the ability to build effective, respectful, working relationships and resolve human resources issues
  • Must be available to work different shifts and weekends and holidays when needed

Capability Requirements:

  • Requires the ability to think from first principles and demonstrates ability to challenge operations processes and use knowledge or trends to look at current situations or problems
  • Has the ability to understand and identify training or developmental needs of staff
  • Able to coach, motivate and be part of a team atmosphere
  • Excellent leadership, supervisory organizational and communications skills
  • Must be able to multi-task, work under pressure and prioritize workload
  • Position is subject to federally mandated drug and alcohol testing

Apply Now:
https://jobs.nationalgrid.com/USA/job/Lowell-Supervisor%2C-TransGas-Dispatch-MA-01854/1186052000/

Transgas Inc. is an Equal Opportunity Employer

Seaside Energy LLC for Woodland Pulp Mill

Baileyville, ME

Location: Baileyville, ME

Transgas provided temporary LNG storage and transportation to an industrial customer that was converting from fuel oil to natural gas. 5 to 6 loads were delivered to the site daily while the mill was tying into the Maritime pipeline. In total, 797 loads of LNG were delivered.

Dates: May to December 2011
Principle in Charge: John Sorota
Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, R. Bevens, H. Bond and E. Kellstrom
Project Status: Completed

National Grid

Location: Rotterdam Junction, NY

Transgas responded to an emergency situation in Rotterdam Junction, NY, where hurricane flooding washed away the existing natural gas pipeline. Transgas responded by providing temporary LNG storage, transportation, and vaporization to the site to provide gas to over 500 customers and a large chemical plant.

Dates: September to December 2011

Principle in Charge: John Sorota

Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, R. Bevens, H. Bond and E. Kellstrom

Vaporizer Equipment: (2) Ambient 60 MCFH vaporizers

Peak flow: 414 MCFD

Project Status: Completed

Tennessee Gas Pipeline/Keyspan Energy

Tennessee Gas Pipeline/Keyspan Energy

Location: Nashua, NH

Transgas provided temporary LNG storage, transportation, and vaporization to support approximately 40,000 residential and commercial customers in the Nashua, NH service territory of Keyspan while routine service was being performed. 6 to 9 loads were delivered daily.

Dates: 21 Days, July 2002
Principle in Charge: John Sorota
Project Team Participants: J. Sorota and D. Batts
Vaporizer Equipment: (3) Heated Vaporizers, (4) Ambient 60 MCFH vaporizers
Peak flow: 7200 MCFD
Project Status: Completed

Duke Energy/Yankee Gas Co.

Location: New London, CT

Transgas provided temporary LNG storage, transportation, and vaporization to support approximately 7000 residential and commercial customers while routine maintenance was performed on the line.

Dates: 3 days, August 2005
Principle in Charge: John Sorota
Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, and E. Kellstrom
Vaporizer Equipment: (3) Ambient 60 MCFH vaporizers
Peak flow: 2,000 MCFD
Project Status: Completed

Tennessee Gas Pipeline/Yankee Gas Co.

Tennessee Gas Pipeline/Yankee Gas Co.Location: Torrington, CT

Transgas provided temporary LNG storage, transportation, and vaporization to support approximately 7090 residential and commercial customers while the Tennessee Gas Pipeline Company performed routine maintenance on the line.

Dates: 7 days, August 2002
Principle in Charge: John Sorota
Project Team Participants: J. Sorota and D. Batts
Vaporizer Equipment: (4) Ambient 60 MCFH vaporizers
Peak flow: 2321 MCFD
Project Status: Completed

Tennessee Gas Pipeline/UNITIL

Tennessee Gas Pipeline/UNITIL

Location: Fitchburg, MA

Transgas provided temporary LNG storage, transportation, and vaporization to support the towns of Lunenburg, Fitchburg, Westminster, Gardner, Townsend, and Ashby while 5.5 miles of 6” pipe was replaced with 12” pipe. Severe weather prolonged this job.

Dates: May to August 2009
Principle in Charge: John Sorota
Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, R. Bevens and E. Kellstrom
Vaporizer Equipment: (2) Heated Vaporizers, (2) Ambient 60 MCFH vaporizers
Peak flow: 2520 MCFD
Project Status: Completed

Algonquin Gas Transmission/Keyspan Energy

Algonquin Gas Transmission/Keyspan Energy

Location: Braintree, MA

Transgas provided temporary LNG storage, transportation, and vaporization to support residential and commercial customers in the Braintree, MA service territory of Keyspan while routine service was being performed. 3 to 8 loads of LNG were delivered daily.

Dates: May 2001 – August 2001
Principle in Charge: John Sorota
Project Team Participants: J. Sorota and D. Batts
Vaporizer Equipment: (3) Heated Vaporizers, (4) Ambient 60 MCFH vaporizers
Peak flow: 6500 MCFD
Project Status: Completed