Location: Baileyville, ME
Transgas provided temporary LNG storage and transportation to an industrial customer that was converting from fuel oil to natural gas. 5 to 6 loads were delivered to the site daily while the mill was tying into the Maritime pipeline. In total, 797 loads of LNG were delivered.
Dates: May to December 2011
Principle in Charge: John Sorota
Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, R. Bevens, H. Bond and E. Kellstrom
Project Status: Completed